November 2015 -- Decided to build with Ryan Homes
December 7 -- Signed our life away
December 9 -- NVR Mortgage Appointment
December 15 -- Interior Selections
December 21 -- Guardian Appointment / Exterior Selections
January 2 -- Flooring Appointment
January 15 -- NVR brokered us to George Mason Mortgage
February 8 -- Pre-construction meeting
February 13 -- Broke Ground
February 18 -- Footers
February 21 -- Foundation walls
February 25 -- Underground septic, water lines, and drain pipes
March 1 -- Wood delivered
March 3 -- basement floors poured and dirt back-filled
March 5-8 -- Framed House
March 10 -- Roof Shingled
March 11-14 -- Plumbing and Central Air
March 15 -- Electric
NEXT UP: PRE-DRYWALL set for March 21