Timeline

November 2015 -- Decided to build with Ryan Homes

December 7 -- Signed our life away


December 9 --
NVR Mortgage Appointment 


December 15 -- Interior Selections 

December 21 -- Guardian Appointment / Exterior Selections 


January 2 -- Flooring Appointment 


January 15 -- NVR brokered us to George Mason Mortgage


February 8 -- Pre-construction meeting

February 13 -- Broke Ground

February 18 -- Footers 

February 21 -- Foundation walls

February 25 -- Underground septic, water lines, and drain pipes

March 1 -- Wood delivered

March 3 -- basement floors poured and dirt back-filled

March 5-8 -- Framed House

March 10 -- Roof Shingled 

March 11-14 -- Plumbing and Central Air

March 15 -- Electric


NEXT UP:  PRE-DRYWALL set for March 21